Troubleshooting

Find your Boba check's title below to see why Boba posted it and what to do next.

Nothing ran

Add a card to run on Boba

Your account has no card, so Boba cancelled the workflow run. Add a card from the link in the check, then re-run the workflow.

Spend limit reached

You reached the monthly spend limit you set. Raise or remove it on Usage & Billing in the dashboard, then re-run the job.

Nothing ran: check the Boba step's settings

Your Boba step's working-directory, config and project point at no suite with tests. Fix those inputs in the workflow, not your test code. Then run npx playwright test --list with the same settings and check that it lists your tests. Boba bills this run.

No Boba run in this job

Your job ran on coldtea-boba, but none of its steps called coldteadotai/boba@v1, so Boba has no result to post. GitHub shows how the job ended. Replace the step that runs Playwright with the Boba step, or move the job back to its old runner.

Boba didn't answer this step, so nothing ran

Boba failed, not your code. Re-run the job. Boba doesn't bill it; if it shows on your bill, tell us and we refund it.

No longer waiting

Boba never started the job. Re-run it.

Your app or tests didn't start

The app didn't start / Couldn't run your tests

Your app or your Playwright setup failed before any test ran. Boba shows the error in the check, with a prompt for your coding agent. When the error names a missing environment variable, add it to your repository's Actions secrets and re-run. Boba bills this run.

The app didn't start on Boba's machine

Boba ran nothing, counts this as its own failure and doesn't bill the run. Re-run the job, and Boba runs it like a first run.

Boba stopped the job

Boba stopped this job at 60 minutes

On Standard: this suite needs longer than that. Add turbo: true to the Boba step to run it faster, or split it into shards.

On Turbo: split your suite into shards so each Boba job finishes within 60 minutes.

If your Boba step sets a shorter timeout-minutes, the check names that limit instead.

On Standard, this suite will take longer than 60 minutes

Boba shows this while the suite runs, when the time your earlier runs took says it won't finish within 60 minutes on Standard. Add turbo: true to run it faster.

Boba failed, not your code

Boba hit a failure of its own. It doesn't bill the run. Re-run the job.

Boba could not run N tests

Boba failed those tests on its side, not in your code, so it doesn't bill them. Re-run the job.

Boba stopped at …

Boba lost contact with your job and stopped it at the stage the title names. Re-run the job.

Cancelled by Boba

Boba lost contact with your job and cancelled the workflow run. Boba says in the check whether it billed the run. Re-run the workflow.

Boba did not post a result

The job ended before Boba posted its result. Open the job on GitHub to see which step ended it.

Secrets

The full report was withheld: it held a secret from this job

Boba found one of your job's secrets in the report and withheld it, so no one can open it. Find where your tests print or save that value, in a log, a trace or an attachment, and stop them.

Boba could not check it for this job's secrets

Boba couldn't check the report for secrets, so it withheld the report and doesn't bill the run. Re-run the job.

Boba found a secret from this job in your setup

One of your job's steps left a secret behind, and Boba says where in the Boba setup check. Delete it in the step that writes it, or before the Boba step. Boba keeps your test result as it is and runs your next push at normal speed.

Pull requests from forks

Boba doesn't run pull requests from forks on this repository yet

Re-running won't help. Boba still runs your pushes and same-repository pull requests.